A leading international law firm Wragge & Co is now working from 250,000 square foot premises housing a £450,000 catering facility to feed its staff. Extensive catering facilities were required for the operation, so foodservice design consultants Humble Arnold were brought in to draw up the plans.
ScoMac were awarded the project by main contractor Wates on a ‘design & build’ contract, taking the original Humble Arnold design intent and providing a ‘value engineered’ option with the view of making savings for the client without devaluing the original intent.
ScoMac offered a number of cost-saving options, which included custom kitchen fabrication and bespoke servery counters produced by itself and a number of alternative suppliers for the prime cooking, refrigeration and warewashing items.
The client and main contractor opted to go with the ScoMac-manufactured elements but decided to retain the core of what was originally specified for the main kitchen equipment.
That included cooking equipment from Ambach, Baron and Rational, as well as refrigeration from Foster. The overall specification for the whole building was very high and this was maintained across all areas of the installation that ScoMac completed.